2 weekly update:
“At last we seem to have come out of the
monsoon period and we can start to produce some work without the need to don
sub-aqua gear every day! Progress to the underground floor slab is nearly
complete with the last section going to be poured by the end of June. the
columns and floor slab above the basement are already underway and the first
section of building has now appeared above ground.
I’m sure you will have been aware of the
temporary traffic lights in Upper Brighton Road over the course of the last
week. This has been unfortunately necessary while UK Power Networks brings the
electric cable from the road into the new sub-station. The final piece to the
jigsaw is to repair the footpath and the road can be fully opened again. This
should be by the end of June. May we extend our apologies for any inconvenience
this work has caused.
Next week we will be concentrating on
preparing the ground floor slab over the basement and preparing the first floor
slab to phase 1 for the delivery of the steel roof later on in July. Here’s to a
rain free July!”
Robert Siddens
Project Manager
Southern Home Counties