Saturday 30 June 2012

Update Royal Star & Garter 26-6-12


From: Robert.Siddens@morgansindall.com [mailto:Robert.Siddens@morgansindall.com]
Sent: 26 June 2012 13:11
Subject: Royal Star & Garter Surbiton 91M005

2 weekly update:

“At last we seem to have come out of the monsoon period and we can start to produce some work without the need to don sub-aqua gear every day! Progress to the underground floor slab is nearly complete with the last section going to be poured by the end of June. the columns and floor slab above the basement are already underway and the first section of building has now appeared above ground.

I’m sure you will have been aware of the temporary traffic lights in Upper Brighton Road over the course of the last week. This has been unfortunately necessary while UK Power Networks brings the electric cable from the road into the new sub-station. The final piece to the jigsaw is to repair the footpath and the road can be fully opened again. This should be by the end of June. May we extend our apologies for any inconvenience this work has caused.

Next week we will be concentrating on preparing the ground floor slab over the basement and preparing the first floor slab to phase 1 for the delivery of the steel roof later on in July. Here’s to a rain free July!”


Robert Siddens
Project Manager
Southern Home Counties